After the dam of the Kakhovka HPP was blown up and the Kakhovka Reservoir ceased to exist, the water intake facilities of the SPS were on land and far from the Dnipro River channel. This made it impossible for the PPS and the Verkhnia Tarasivska irrigation system to provide technical water for irrigation to both NSP-10 and NSP-12 water users and others.
Project Objective: To unite the irrigation systems and the basin by laying a pipeline of appropriate capacity, renovating the existing one and building a new pumping station at the regulating basin of the Rozumivska irrigation system.
Effect:
✅ Meeting the water needs of farms and residents of the settlements of Mariivka, Smoliane, Novosergiivka, Udilenske in Zaporizhzhia district
✅ Increase in the area served by the irrigation system
✅ Reducing the cost of water in these settlements
Need:
➡️ Financial: funds for repair and construction works
➡️ Technical: development of technical documentation, construction machinery and related equipment for construction works
➡️ Logistics: delivery of the necessary equipment and machinery to the location where the work is planned
Total project cost: EUR 2.2 million.